Eight findings from the 171-page SAHRC Inquiry Report on water and sanitation service delivery in Gauteng, released 3 November 2026 — with implementation deadlines of 1 to 12 months
The inquiry was held over three days — 19 to 21 May 2026 — following persistent community complaints. Eight of nine WSAs appeared before the panel; Rand West City defied its subpoena and submitted only written information after hearings. The SAHRC has stated it will pursue litigation where recommendations are not implemented.
Finding 1
UIFW Expenditure & Accountability
All 9 WSAs must investigate and address all unauthorised, irregular, fruitless and wasteful expenditure under MFMA Section 32 — recovering lost monies and instituting disciplinary or criminal proceedings. AGSA is to monitor compliance and submit a consolidated report to the SAHRC.
Target: All 9 Gauteng WSAs · Auditor-General (AGSA)
WSAs report to AGSA: 3 months
AGSA to SAHRC: 6 months
Finding 2
Financial Recovery Plans for Distressed Municipalities
Three severely financially distressed municipalities must approach National Treasury's Municipal Financial Recovery Service for financial assessments and mandatory recovery plans focused on revenue collection, expenditure control, and debt relief or restructuring under MFMA sections 153–155. Merafong owes Rand Water R1.5bn; Emfuleni had a R0 water capital budget for two consecutive years.
Target: Rand West City · Merafong City · Emfuleni · National Treasury MFRS
Approach MFRS: 1 month
MFRS progress report: 6 months
Finding 3
Filling Critical Technical Vacancies
Municipalities must identify all critical technical vacancies — engineers, scientists, process controllers, and artisans — and report whether positions are unfunded or vacant due to recruitment challenges. DWS and Gauteng CoGTA must provide targeted technical support or secondments without creating indefinite external dependency.
Target: Rand West · Emfuleni · Mogale City · Merafong · Tshwane · Ekurhuleni · DWS · Gauteng CoGTA
Vacancy report: 3 months
Finding 4
Water Tanker Regulation Framework
Institutions must jointly formulate standards and guidelines for operating water tankers and static communal tanks — covering water quality testing, fair pricing benchmarks, and anti-corruption controls. Temporary arrangements must include explicit transition plans to permanent reticulated pipe networks, except where physical constraints like dolomite make piping unfeasible.
Target: DWS (lead) · Gauteng CoGTA · City of Johannesburg · City of Tshwane · City of Ekurhuleni
Joint framework report: 6 months
Finding 5
Wastewater Treatment Works Recovery Programme
DWS must shift from ad-hoc responses to a province-wide, risk-prioritised recovery programme for failing wastewater treatment works, based on health risks and downstream impact. CSIR is to be engaged for independent scientific expertise and fit-for-purpose treatment solutions.
Target: Department of Water and Sanitation · CSIR · Affected WSAs
Priority list: 3 months
Implementation plans: 6 months
Progress report: 12 months
Finding 6
Environmental Rehabilitation of Rivers & Dams
DFFE and DWS must jointly develop a prioritised rehabilitation programme for rivers, wetlands, and dams — including Hartbeespoort Dam and the Vaal and Crocodile catchments — degraded by raw sewage spillages. Civil society organisations and private sector partners must be engaged.
Target: Dept of Forestry, Fisheries & Environment · DWS · Relevant wastewater operators
Programme initiation: 3 months
Programme plan: 6 months
Progress: 12 months
Finding 7
Protecting Infrastructure from Theft & Vandalism
WSAs and Rand Water must identify high-risk hotspots and recurring targets of vandalism and theft, sharing intelligence with SAPS. SAPS must integrate water infrastructure into its specialised Essential Infrastructure Task Teams for intelligence-led policing and preventative operations.
Target: All Gauteng WSAs · Rand Water · South African Police Service (SAPS)
Implementation reports: 3 months
Finding 8
Bulk Supply Resilience & Reservoir Buffer Assessment
Rand Water must conduct a targeted vulnerability assessment of its bulk system — covering power failure risks, single failure points, maintenance needs, and backup power. Each municipality must evaluate local reservoir storage capacity. DWS must assess whether updated national guidelines on minimum reservoir storage buffers are required. A February 2026 failure at Rand Water's Palmiet and Zuikerbosch pump stations highlighted systemic vulnerability.
Target: Rand Water · DWS · All supplied Gauteng WSAs
All parties report: 3 months
Gauteng's water crisis stems from infrastructure failure — the DWS confirmed that sufficient water resources exist. But Emfuleni ran a R0 water and sanitation capital budget for two consecutive years, Rand West City lost 58% of its water yet defied a subpoena, and the SAHRC has warned it will pursue litigation if all eight findings go unimplemented.