Western Cape data centre milestones by facility, operator type, and load disclosure status, 2009–2026+
January 2009
Carrier-neutral · Teraco
Disclosed load
Teraco CT1 opens in Rondebosch — Cape Town's first carrier-neutral colocation facility
The Great Westerford building provides 5 MVA and 2,600 m² of technical space. Over the next decade, CT1 undergoes four further expansion phases. All capacity and footprint metrics are publicly disclosed.
October 2010
Telecom · Internet Solutions
Confidential load
Bree Street facility enters operation under Internet Solutions (now OADC CPT3)
The carrier-managed site at Bree Street becomes Cape Town's key telco interconnect node. Exact IT load and white-space figures are not publicly disclosed — a pattern that holds across every telecom-operated site in the city's ecosystem.
October 2021
Carrier-neutral · Teraco
Disclosed load
Teraco CT2 Phase I opens in Brackenfell — the Western Cape's first large-scale disclosed hyperscale campus
Construction began March 2020; Phase I delivers 18 MW critical IT load in an 8,000 m² data hall within a 25,000 m² building. Full capacity, utility feed, and footprint metrics are published — establishing the benchmark for Cape Town load transparency.
December 2022 – January 2023
Carrier-neutral · OADC (WIOCC)
Confidential load
OADC launches two Cape Town facilities in quick succession — Rondebosch and Brackenfell
Backed by WIOCC's $200 million pan-African raise (November 2021), OADC CPT1 (Rondebosch, up to 5 MW site load) goes live in December 2022 and CPT2 (Brackenfell) in January 2023. CPT2's IT load is not publicly disclosed; CPT1 site-load figures are partial only.
January – March 2023
Carrier-neutral · Africa Data Centres
Under development
ADC breaks ground on CPT2 (Atlantic Hills, 20 MW) and signs a 20-year solar PPA for CPT1
CPT2 is announced as eight data halls, up to 15,000 m², targeting mid-2024 go-live. Simultaneously ADC CPT1 signs a solar power purchase agreement with Distributed Power Africa — the first publicly documented renewable wheeling arrangement for a Cape Town data centre.
Mid-2024 – July 2024
Carrier-neutral · Africa Data Centres
Disclosed load
ADC CPT2 goes live (20 MW) and CPT1 doubles to 11.5 MW — the ecosystem's disclosed-load cluster reaches its peak density
CPT2 opens at 20 MW IT load across 12,000 m² of white space. On 25 July 2024, CPT1's 6 MW expansion completes, adding three halls and 1,000 racks to bring total IT load to 11.5 MW. Both facilities publish capacity, footprint, and utility data in full.
November 2025
Carrier-neutral · Teraco
Disclosed load
Property developer · Cavaleros
Announced only
Teraco CT2 hits 50 MW after Phase II; CT1 expansion begins — and Cavaleros announces a 360 MW Cape Town campus with no location, no date
CT2 Phase II completion (14 Nov) brings total critical IT load to 50 MW on a 90 MW utility feed — the largest fully disclosed campus in the Western Cape. The CT1 +2 MW expansion (targeting early 2027) is confirmed the same week. On 11 November, Cavaleros Group unveils Cosmas Data Cities: a proposed 360 MW, 100 ha Cape Town campus with no confirmed location, no construction date, and no utility agreement disclosed.
December 2025
Carrier-neutral · OADC
Confidential load
OADC acquires seven NTT/Internet Solutions South Africa data centres, absorbing Bree Street into its network as CPT3
The Bree Street facility — operational since 2010 — transitions from telecom-managed to carrier-neutral under OADC, gaining a second operator classification but retaining undisclosed IT load figures. The acquisition consolidates three Cape Town nodes under one operator for the first time.
1 April 2026
Hyperscale · Equinix
Under development
Equinix announces R7.5 billion SA investment: two Cape Town campuses totalling 160 MW — the largest single power commitment in Western Cape history
Land acquired at King Air Industria (the former King David Golf Club) for a combined 120,000+ m² campus. The 160 MW combined peak demand — undisclosed per-site — would nearly triple Cape Town's current disclosed colocation capacity. Within two weeks, civil society groups (Foxglove and the Housing Assembly) file a rezoning objection citing undisclosed water and electricity demand figures.
July – October 2026
Hyperscale · Equinix
Under development
City planning tribunal approves Equinix rezoning (14 July) — but mayoral sign-off remains pending, construction not yet authorised
The City of Cape Town's planning tribunal clears the King Air Industria rezoning application. Mayor Geordin Hill-Lewis has not yet signed the approval; both Cape Town facilities remain at the permitted-but-not-started stage. The 160 MW demand estimate cited in tribunal documents remains a maximum-scenario figure; per-site MW allocation is not publicly split.
Every Western Cape facility with a fully published critical IT load is carrier-neutral and predates 2024. Equinix (160 MW) and Cavaleros/Cosmas Data Cities (360 MW) have disclosed neither per-site megawatt figures nor utility agreements, meaning roughly 31% of Cape Town's peak municipal demand could be committed before a single rack is energised.