Mogale City slashed its capital budget by 21% while its sewage works collapsed

Approved Capex budgets · Mogale City Local Municipality · 2021/22–2024/25. DWS grant for Percy Stewart WWTW repairs shown for scale.

R22.5m
actually budgeted for Percy Stewart WWTW repair in 2024/25
R150m
allegedly earmarked for a new municipal office block the same year
Capex budget
R35m DWS grant (WWTW)
Mogale City's capital budget nearly doubled between 2021/22 and 2023/24 before reversing sharply — even as raw sewage flooded communities along the Bloubankspruit and Crocodile rivers. DWS grant funds meant for wastewater repairs appear to have been misapplied, while the municipality allegedly prioritised a R150m office block over the R80m needed to fix the Percy Stewart plant.